Air conditioning of the gearbox and transfer case testing room of the company TATRA TRUCKS a.s.
As part of the modernization of the technological facilities of the testing facilities, a extraction system for the gearbox and differential testing facility was delivered to TATRA TRUCKS a.s.. The project was implemented as part of a subcontract for AVL Moravia s.r.o., which provided the delivery of comprehensive testing technology.
The main purpose of our project was to supply an exhaust system, the task of which was to remove residual heat from the test room and from the switchboards during the test sequence. The solution was designed as part of a comprehensive ventilation of halls, where high thermal loads occur due to load tests of gearboxes and differentials.
The increase in temperature during testing can negatively affect the stability of measurements, the reliability of electrical equipment and the comfort of the operator, therefore the aim was to ensure effective and operationally reliable heat dissipation.
Technical solution proposal
The designed system was based on the principles of modern industrial ventilation with an emphasis on targeted extraction of warm air directly at its source. The solution included:
-
exhaust branches from the test area,
-
separate exhaust from electrical switchboard areas,
-
use of exhaust hoods for local heat capture,
-
connection to pipework with industrial fans.
The entire system was designed to ensure stable performance throughout the test cycles and minimize pressure losses and energy consumption of operation.
Implementation as part of a subcontract
The implementation took place in close coordination with AVL Moravia s.r.o., with the extraction system being fully integrated into the supplied test facility technology. The installation took place with respect to the existing layout of the hall and without restrictions on other technological processes.
Důraz byl kladen na:
The emphasis was on:
-
operational reliability of the system,
-
noise reduction,
-
easy maintenance and accessibility of industrial air conditioning components.
Benefits of the solution
The implemented solution brought a significant reduction in the thermal load in the test room and around the switchboards. Thanks to effective extraction and appropriately designed hall ventilation, operating conditions were stabilized, operational safety increased, and the working environment for the operator improved.
Conclusion
The delivery of the exhaust system for the gearbox and differential testing room, implemented as a subcontract for AVL Moravia s.r.o., represents a functional solution based on the principles of industrial air conditioning, effective hall ventilation and the use of exhaust hoods. The project underlines the importance of properly designed ventilation as a key element of modern industrial operations.
If you are looking for the right technical solution that could improve the quality of the working environment or exhaust, do not hesitate to contact us.
-
Realization year:2024
-
Focused at: